The main task was to continue Dernburg’s design using a contemporary language of symbols and the characteristic dynamics of the era to balance the scale of the building. The coherence of the old and new parts was achieved through the right proportions, mass reduction, horizontal divisions and the properties of the materials. The dynamism of the unambiguously horizontal façade of the new part was intensified by the fan-like deflection of the cornices. The background, made up of glass and fibre cement panels, corresponds to the ceramics of the historic edifice. The two parts of the building are connected through an entrance atrium.
Modernization and expansion of the ‘Renoma’ department store ; Wrocław, 40 Świdnicka St.
Author of the building: | Hermann Denburg |
Project authors: | Maćków Pracownia Projektowa: Zbigniew Maćków (Chief Architect), Piotr Wilk (Lead Architect), Juliusz Ederman, Marta Firganek, Paweł Kirschke, Marek Kotowski, Piotr Krynicki, Piotr Zybura; cooperation: Jacek Brzezowski, Agnieszka Gilarska, Michał Hawrylak, Jarosław Jodkowski, Katarzyna Korsak, Marcin Macuta, Adam Markuszewski, Marta Mnich, Piotr Sulisz, Maciej Witaszek, Bartosz Zięba |
Retail concept: | Benoy – Rob Bishop, Pete Challoner |
Interior design: | Benoy – Michelle King, Paulin Long |
Construction: | Ove Arup & Partners International Limited |
Executive design: | Maćków Pracownia Projektowa: Jerzy Kopka (Lead Architect), Karolina Bielak, Anna Jagoda-Major, Agata Kowalczyk, Marta Maślanka, Eliasz Matuła, Mariusz Maury, Alicja Mołyń, Michał Nykiel, Bartłomiej Witwicki, Zuzanna Wojtasiak, Bartosz Zięba, Piotr Zybura |
Fittings and fixtures: | Ove Arup & Partners International Limited |
Conservator`s supervision: | Krystyna Kirschke |
Replica of the sculptures: | Paulina Pokorny-Zięba |
Visual Identity, Logo: | Maćków Pracownia Projektowa: Zbigniew Maćków (Chief Architect), Bartosz Zieliński, Anna Zięba, Bartosz Zięba, Piotr Zybura |
Investor: | Centrum Development & Investments Polska |
Contract engineer: | Ove Arup & Partners International Limited |
General contractor: | Warbud |
Build-up area: | 10 726 m2 |
Usable area: | 77 769 m2 |
Total area: | 99 531 m2 |
Cubage: | 381 786 m3 |
Project date: | 2005 |
Realization date: | 2009 |
Koszt inwystycji: | 100 mln euro |
Pictures: | Krzysztof Smyk, Juliusz Sokołowski, MPP |